Load Attendance Data

Manager Guide

Version
R2025.2.1
ft:lastEdition
2025-12-01
Load Attendance Data

To load attendance data: 

  1. Go to Attendance Management.
  2. In the Load panel, do the following:
    1. Use the Organization setting to select a location.
    2. (Optional) Use the Manager setting to load employee attendance data based on the manager that they report to.
    3. Note: You can’t use this setting if the location that you select in the Organization field has no assigned managers.
    4. Use the Period Start and Period End fields to specify the date range that you want to load.
  3. Click Load.

Dayforce shows any attendance data that occurred between the selected dates in the Incidents, Violations, and Grades tabs.