KPI Day Part Aggregation

Dayforce Implementation Guide

Version
R2026.1.0
ft:lastEdition
2026-03-03
KPI Day Part Aggregation

This background job aggregates KPIs by sections of the day (that is, day parts) when importing KPI data. After mapping KPI data to day parts, administrators can run the KPI Day Part Aggregation background job to aggregate these KPIs by their day parts.

For example, the Sales KPI contains data about sales throughout the day. Administrators can use this task along with the configuration of the KPI settings in Schedule Setup > Day Part to separate the KPI by the day parts of Breakfast Sales, Lunch Sales, and Dinner Sales, without having to separate it manually before importing it. See Configure Day Fragments.

KPI Day Part Aggregation job settings
Setting Description
Site The sites whose KPI data will be used by the background job.
Name The task’s descriptive name.
Start Date The start of the date range of the KPI data to aggregate.
End Date The end of the date range of the KPI data to aggregate. This can be the same day as the day specified in the Start Date setting.
Source KPI The source KPIs to aggregate.

Schedule the KPI Day Part Aggregation Job

If you schedule the KPI Day Part Aggregation background job, Dayforce shows the following settings:

KPI Day Part Aggregation scheduled job settings
Setting Description
Site The whose KPI data will be used by the background job.
Name The task’s descriptive name.
Offset Start (Days) The number of days from the current date in which the aggregation starts. Enter 4 to start the evaluation four days from the current date. You can also enter 0 to start the evaluation on the current date or a negative number to evaluate days in the past.
Length (Days) The total number of days that the job evaluates.
Source KPI The source KPIs to aggregate.